18 maart 2026



Following the earlier phases, including design, foundation works and steel construction, the project has now entered an important next stage.
Progress:
✅ Farrowing house: Slatted floors with underfloor heating for piglets was installed; piping was connected to provide the piglets with a comfortable warm space.
✅ Gestation house: windows and sandwich panels are installed in the client’s colors, high-quality ventilation ceiling is completed, air scrubber is prepared for future expansion; interior finishing with trespa provides durability and a neat finish.
✅ Central corridor: prefab walls and drainage channels are installed; concrete pouring is planned; which ensures a hygienic, easy-to-clean area for efficient barn management.
In the coming weeks, we will install control valves and finalize technical installations, bringing the stable closer to full operational status.
Through this phased approach, we are building a sustainable, efficient, and animal-friendly facility, where technology, hygiene, and animal welfare come together.