7 mei 2026



The stable will feature free-farrowing pens and will be equipped with manure scrapers, supporting both efficiency and animal welfare.
The first phase has now been completed – a key milestone in the project. All concrete pit walls have been finished, totaling nearly 3 kilometers of concrete walls.
Work is now progressing on the flooring systems:
✅ Installing concrete slatted floors with integrated (leak-tight) air channels
✅ En-Sta (Germany) will be applying plastic flooring systems
Meanwhile, the first 16-meter wooden roof trusses have arrived on site.
Next up? Assembling the steel and timber structure, bringing the building further to life.