The first construction phase for the machine hall and workshop has been completed:
✅ Foundations installed
✅ Steel structure assembled
✅ Roof and wall cladding completed
A unique aspect of this project is the difference in ground level across the site. One side of the building is positioned approximately 1.5 metres below ground level. To protect the structure from moisture penetration, an additional waterproof barrier has been installed along this exterior wall.
The next phase will focus on:
🔹 Pouring approximately 2,250 m² of concrete flooring
🔹 Preparing the building for further completion and use
It’s great to see this project taking shape step by step. We thank Aalberts Krap for their trust and look forward to the next construction phase. 🤝